Concrete calculator guide
What does this calculator help you figure out?
A concrete estimate starts with the space you are filling: length, width, and finished depth. This calculator converts the depth from inches to feet, multiplies the three dimensions to find cubic feet, adds your waste allowance, and shows the result in cubic yards. That sequence matters because ready-mix concrete is commonly ordered by the cubic yard, while the measurements on a tape measure are often a mix of feet and inches. Use the planned concrete depth, not the thickness of the gravel base below it. For a slab, measure the inside length and width of the pour area. For a footing or path, use the actual run of concrete. The shape selector also handles footings, walls, steps, and round columns, and optional fields add extra sections, formwork, reinforcement, and material prices. The result is a planning estimate, so confirm access, minimum delivery quantities, product yield, and site conditions with the supplier before placing an order.
How is the result calculated?
Base volume (ft³) = length (ft) × width (ft) × depth (in) ÷ 12. Adjusted volume (yd³) = base volume (ft³) × (1 + waste ÷ 100) ÷ 27. Bags = adjusted volume (ft³) ÷ bag yield (ft³/bag), rounded up.
Worked example
Worked example with the default slab: a 10 ft × 10 ft pour that is 4 in deep has a base volume of 10 × 10 × (4 ÷ 12) = 33.33 ft³, which is 33.33 ÷ 27 = 1.23 yd³ before waste. Adding the default 10% allowance gives 33.33 × 1.10 = 36.67 ft³, and 36.67 ÷ 27 = 1.36 yd³, the recommended order the calculator displays. The metric line shows 36.67 × 0.0283168 = 1.04 m³. The bag row divides the same 36.67 ft³ by the default 0.6 ft³ yield of an 80 lb bag: 36.67 ÷ 0.6 = 61.1, rounded up to 62 bags. Actual bag yield varies by product, so change that field to match the label.
Units and conversion notes
Enter length and width in feet and depth in inches, as labeled. Four inches is 4 ÷ 12 = 0.333 ft. Do not multiply feet by inches without converting first. One cubic yard equals 27 cubic feet, and the calculator uses 0.0283168 cubic meters per cubic foot for the metric display. Bag yield is entered in cubic feet per bag, reinforcement in linear feet, and formwork in square feet.
What does the result mean?
The concrete calculator returns a quantity to buy, not a guarantee of coverage. Substrate condition, waste from cuts, spillage, and settling all push real consumption above the theoretical figure, which is why most trades order a margin on top. Check the coverage rate printed on the product you actually purchase, because it varies between brands and mixes. On this page the figure rests entirely on project shape, length / diameter, width / height, depth / thickness, step count, step run, step rise, additional rectangular sections, additional section length, additional section width, additional section depth, optional formwork area, formwork allowance, optional reinforcement length, reinforcement stock length, reinforcement allowance, waste allowance, 80 lb bag yield, ready-mix price, 80 lb bag price, delivery cost and material tax, so start there if the concrete calculator returns something you did not expect.
Common mistakes to avoid
Waste covers small measurement errors, spillage, uneven forms, and site loss; it does not correct a wrong depth or an undersized form, so the single largest error on this page is entering the depth of the gravel base or the total excavation instead of the finished concrete thickness. Measure the finished pour, keep all dimensions in their labeled units, and round a purchase up rather than down when a shortage would stop the job. For steps and walls, remember the calculator treats them as planning shapes, not engineered designs.
Construction quantities are planning estimates. Confirm product yield, waste, site conditions, structural requirements, and local code with the supplier or qualified professional.